|

The following news article was printed
in the Winter 2001 issue of The Balance Sheet, the newsletter of
the National Environmental Balancing Bureau (NEBB)
and reproduced with their permission.
Discipline Spotlight: Building
Systems Commissioning
University of North Dakota and Building System Commissioning
| By |
Randall Bohlman
Technology Advancement Coordinator at University
of North Dakota
Facilities - Design & Engineering
|
The University of North Dakota - Facilities Department,
Environmental Engineering, and EAPC (a local engineering firm) of
Grand Forks, North Dakota, developed Building Commissioning Procedures
in the early 1990s after it became apparent that the Design
- Bid - Build form of construction was not delivering end results
that the University of North Dakota (UND) desired.
Prior to 1990, it was quite common for the Facilities
Department to spend up to two years and go through two complete
heating and cooling seasons before all heating and cooling issues
were corrected. On multiple occasions we retained the services of
Environmental Engineering (a NEBB contractor) to verify the work
other balancing contractors had done and to help us determine problem
areas. In many cases, prior to using NEBB firms, it became apparent
that test and balance (TAB) work was not performed to the level
of quality needed to identify problems that prevented building HVAC
systems from operating properly. It was common to find problems
with the original design, installation, startup, and maintenance
issues after a building was constructed. Even though most of the
design, specification, and construction problems were eventually
solved, UND Facilities (the owner) would have to absorb these costs.
Building occupant complaints during this two-year period also were
excessive.
We realized that a different approach to HVAC construction
projects had to be developed.
Environmental Engineering proposed, and UND and
EAPC adopted, a four part process to improve the design and construction
process on larger projects.
Phase I
The Commissioning process starts with a review
of the project during the design phase. The purpose of this review
is to spot problems that would prevent the HVAC systems and buildings
from operating properly. This review begins early in the design
stages and is done before the bid process is complete. The commissioning
review checks for acceptable velocities in pipes, ducts, coils,
equipment and registers. System Effect on fans is also evaluated.
Duct and piping, details and specifications are also reviewed to
assure that proper installation
techniques are written and detailed in the plans
and specifications. This review process has greatly reduced design
problems that show up during startup and are either impossible,
or costly, to fix after the fact.
It is important to engage the building system commissioning
(BSC) team member early in the design phase. UND initially started
the design review after the project was bid. This caused a confrontational
relationship to develop between the design professional and the
BSC firm. Changes made to the design after the project was bid also
caused costly change orders to be generated.
Bringing the owner, design team and the BSC together
during the design phase has eliminated this stumbling block. The
engineering firm is also given the review guidelines to follow before
the design begins. This review gets the entire team involved so
that all concerns are addressed before the project is bid.
Phase II
The second phase of the BSC process involves weekly or biweekly
inspections of the duct, piping systems and equipment installation.
The purpose of this inspection is to insure that the details and
specifications outlined in the design process are followed.
It is important to have a pre-construction meeting
with the engineer, owners representative, BSC agent and the
Mechanical and HVAC contractors. The purpose of this meeting is
to discuss the inspection process and to show the mechanical contractor
details and specifications that will be inspected. Once the contractors
understand the methods that will cause a test to pass or fail, their
work is usually performed in a manner that allows tests to be passed.
Phase III
Phase III involves the startup of equipment and the testing adjusting
and balancing of the mechanical systems. Although the Mechanical
contractor is responsible for the startup of all equipment, UND
observes and monitors all startups.
Test and Balancing of all mechanical systems starts
once all equipment and controls have been started and are running.
UND spot-checks final TAB readings for accuracy. When TAB firms
realize that we are serious about the quality and accuracy of TAB
test readings, balance problems were reduced.
UND has found it beneficial to bid and issue separate
contracts for test and balance work. This gives UND more control
over the firm selected and does not put the TAB contractor under
the control of the Mechanical Contractor that is being inspected.
We have also placed a NEBB-only inclusion in our
TAB specifications. The NEBB qualification, separate contract, and
random spot-checking have significantly reduced the times that non-qualified
TAB firms are selected to work for UND. Building systems are now
set up according to design requirements.
Phase IV
The fourth phase of the commissioning process involves a complete
check out of the control system, a verification of control loop
operation, and a point-to-point check of all control points. Facilities
personnel from UND and the control contractor perform these tests
to insure proper operation.
Once this phase of the process has been completed,
final O & M instructions are given with the BSC, TAB, control
and mechanical contractors giving individual lessons on the system
operation.
While it may seem that this is a long and involved
process we have the following results to show for it:
- Design and construction related problems are reduced.
- Operational problems are found and corrected while the
project contractor is still onsite and the project is still
within the one-year warranty time frame. Correction costs to
UND are significantly reduced.
- Building occupants move into buildings where problems have
been corrected. Customer satisfaction with the finished project
is higher than before. Occupant complaints with startup issues
have been significantly reduced.
- Control sequences actually perform as designed and specified.
We employ sophisticated control strategies to control occupant
comfort and operating costs. The energy costs per square foot
at UND are well below regional averages. The average energy
usage is 140,883 Btus/SF. The average energy cost at UND
is $0.62/SF. This is 50% to 75% below regional averages for
equal facilities. The University of North Dakotas facilities
exceed 5.2 million square feet. UNDs buildings are comprised
of medical, research, medium to large academic, and housing.
Commissioning works. However, it is not a process
that begins after construction is complete. It starts before bid
day during the design process and runs through the entire project.
It is impossible to successfully operate a building that has inherent
design or installation problems buried within the completed building
structure.
When commissioning is performed using a team approach,
time and money are saved, a superior product is produced, and the
aggravation experienced at project completion is reduced substantially.
Building owners can be assured that the mechanical systems are operating
as designed and at peak efficiency. This process benefits the contractors
as well by enabling delivery of a refined product helping to eliminate
costly callbacks to the job site after construction is complete.
|